Galway Airport – Hangars

Project Description:
Design & Build contract for 2 New Hangars at Galway Airport. This project involved the construction of 2 no. large aircraft hangars (3,800m2) and an extension to the apron at Galway Airport. 150mm deep Marshall Asphalt was installed over a sub-base to an area that had been reduced to formation level involving the removal of limestone rock. These works were completed initially in a restricted landside area and were completed in an airside situation with some works being completed at night.

Client: Corrib Airport Ltd

Architect & Design Team: Simon J. Kelly & Partners Architects Galway ; Engineer (Structural): Coyle Kennedy Consulting Engineers Galway; Project Manager: Steve Cunningham & Associates, Galway

Reference Contact: Simon J. Kelly & Partners

Project Value: circa €3.5 million

Project Size: circa 3,800 m2

Project Duration: 6 months